Create an architecture description that helps people assess firmware behaviour, interfaces and change. Make the relationship between diagrams and engineering claims explicit.

Specialist10 min reading + 25 min practiceWorked example

← Back to the learning library

Before you begin: Read TFA-101 on firmware architecture and TFA-303 on requirements. Bring a diagram that different disciplines interpret differently.

Reading time and practice time are estimates. Examples use fictional products and illustrative engineering values, not approved product limits.

Publication basis: ISO/IEC/IEEE 42010:2022. This module teaches an original firmware application of architecture-description concepts; it does not prescribe a required diagram notation.

Learning objectives

By the end of this module, you should be able to:

  • Distinguish an architecture from the description used to communicate it.
  • Select views according to stakeholder concerns.
  • Check consistency between structural, execution and deployment views.
  • Record architectural decisions, alternatives and evidence.

Lesson 1

1. Separate the design from its description

ISO/IEC/IEEE 42010 concerns architecture descriptions, viewpoints and related concepts. It does not prescribe an architecting method, diagram tool or document format. A description represents an architecture; a well-formatted description does not prove that the architecture satisfies its requirements.

For a fictional battery-powered data logger, the source tree shows implementation organisation but says little about acquisition deadlines, update trust or persistent-data ownership. An architecture description should answer the questions people need to assess. It may combine diagrams, tables, decisions and references to analysis. The value lies in the relationships and reasoning, not the number of views or the sophistication of the modelling tool.

Lesson 2

2. Begin with stakeholders and concerns

Identify who must use the description and what they need to decide. Firmware developers may need dependency and ownership rules. Electronics engineers may need pin states during reset. Verification engineers need controllable interfaces and observable endpoints. Service engineers need compatible image combinations and recovery access. Security reviewers need trust boundaries and authority changes.

A concern should be specific enough to guide a view: “Can a flash erase delay sampling?” is more useful than “performance”. Record the requirement or risk behind the question where possible. Several people can share a concern, and one person can hold several roles. Revisit the list when a new board variant, remote service or external supplier changes who depends on the architecture.

Lesson 3

3. Choose viewpoints before drawing views

A viewpoint establishes how a class of concerns will be represented and interpreted. A view applies that approach to the actual product. In the logger example, an execution viewpoint might define tasks, interrupts, queues, timing annotations and ownership conventions. Its view shows the chosen tasks and their actual communication paths.

Agree the meaning of arrows. A dependency, a message, a power connection and a trust relationship are different things. Avoid a diagram where the same arrow silently means all four. Include a legend or a short modelling convention where ambiguity matters. Use familiar notation when it helps, but choose what the audience can assess rather than requiring UML simply because the publication number appears on the cover.

Lesson 4

4. Build a small set of complementary views

The following is an example view set, not a mandatory list from the standard. Add a view when it answers an important question that the existing set cannot answer clearly.

ViewLogger concernUseful content
Context and interfacesWhat can influence stored measurements?Sensors, service connector, radio peer and trust boundaries
Structure and ownershipWho may change calibration or output state?Components, dependencies and controlled interfaces
Execution and timingCan logging or updating delay acquisition?Interrupts, tasks, queues and bounded blocking
Deployment and recoveryWhich images and boards work together?Memory regions, boot chain, variants and service paths

Reference detailed material rather than copying it into every view. For example, the deployment view can point to the controlled compatibility matrix while showing where compatibility is checked.

Lesson 5

5. Check correspondences between views

Independent diagrams can each look plausible while describing different systems. Check whether a message in the execution view has an interface and owner in the structural view. Check whether a recovery path in the deployment view appears in the security analysis. Check whether the memory map permits the queues and buffers assumed by the timing model.

For the logger, a drawing may suggest that an update worker runs alongside sampling. The processor manual might show that flash operations stall instruction fetch from the same bank. The correspondence review should expose this conflict before a scheduler diagram is accepted as proof of independence. Record unresolved inconsistencies and the work needed to resolve them. A shared component name alone is not evidence that two views agree.

Lesson 6

6. Retain decisions and alternatives

Capture why a choice was made, including the conditions under which it remains valid. A decision to use a single cooperative loop might depend on bounded peripheral transactions and a low acquisition rate. Increasing the sampling rate or adding a blocking library should trigger reconsideration of that decision.

A useful decision record states the concern, relevant constraints, considered alternatives, chosen option, consequences and supporting evidence. Include rejected alternatives when they explain a significant trade-off. Avoid retrospective rationalisation that makes every choice appear inevitable. Architectural debt can be acceptable when its consequences and ownership are understood; it becomes dangerous when the assumptions that justify it disappear from the record.

Lesson 7

7. Keep the description aligned with the release

Architecture descriptions need configuration identity. State which product family, board revisions and software baseline the description covers. Distinguish the current design from a planned future variant. Give diagrams stable identifiers so requirements, reviews and tests can reference them without relying on slide numbers that change during editing.

Use change review to find affected concerns and views. A new DMA buffer can change memory ownership, concurrency and test observability even if the public interface is unchanged. During review, sample implementation paths and compare them with the stated dependency rules. Automated dependency checks can support this work, but they will not reveal every mismatch in physical behaviour, timing or security assumptions.

Decision guide

Which view should answer this question?

QuestionPrimary viewSupporting evidence
Who owns an actuator command?Structure and ownershipInterface contract and code review
Can an interrupt starve a task?Execution and timingResponse-time analysis and target measurements
Can recovery install an unauthorised image?Deployment and trustBoot policy, key protection and negative tests
Which board variants share this driver?Deployment and configurationCompatibility matrix and variant tests

Worked example

Worked example — flash updates interrupting data acquisition

Problem

A logger’s architecture drawing shows separate acquisition and update tasks. The team assumes the tasks can operate independently, but a field update produces gaps in recorded samples.

Engineering approach

The execution view is connected to a memory-bank view and processor constraints. The review discovers that erase operations can stall code execution. The team compares a maintenance-only update mode, execution from an unaffected memory region and a different storage design. It selects maintenance mode for this product, defines entry and exit behaviour, and records the loss of continuous acquisition during authorised servicing.

Result

The architecture description now explains an actual constraint and its product consequence. A target test confirms the maintenance transition and verifies that the system does not label interrupted data as a continuous valid record.

Engineering evidence

What should the work produce?

Stakeholder and concern register

Explains which decisions the description must support.

Viewpoint conventions and views

Define notation, scope, entities and relevant relationships.

Decision and consistency records

Retain alternatives, assumptions and resolved discrepancies.

Configuration-linked architecture index

Identifies the described release and its supporting analyses.

Common failure patterns

What goes wrong?

  • Using an attractive component diagram as the complete architecture argument.
  • Mixing planned and implemented behaviour without distinction.
  • Showing independent tasks while ignoring shared hardware constraints.
  • Updating a diagram without revisiting its dependent analysis.

Applied exercise · approximately 25 minutes

Review an apparently independent diagnostic task

A diagnostic task may request a new sensor conversion while the control task uses the same peripheral. The block diagram places them in separate boxes and labels both “independent”.

  1. Identify three stakeholder concerns that the diagram does not answer.
  2. Propose two views and define the meaning of their arrows.
  3. State one architectural rule and how you would check it.
Review a suggested approach

Relevant concerns include peripheral ownership, disturbance of control timing, and the validity of values reported to service tools. A structural view can show a single acquisition owner and request interfaces; an execution view can show scheduling, request arbitration and completion events. Dependency arrows in one view should not be mistaken for message timing in the other.

An example rule is that only the acquisition owner may reconfigure the peripheral. Diagnostics request a bounded operation through that owner and receive an explicit busy or completed result. Check the rule by reviewing access paths and by testing diagnostic traffic during worst-case control activity. The architecture must also explain what happens when a request cannot be served within its permitted time.

Completion criteria

  • Concerns connect to real decisions and stakeholders.
  • View conventions distinguish structure from execution.
  • The rule has both an owner and a credible verification approach.

This is a self-directed engineering exercise, not an accredited examination. Compare the rationale as well as the final answer.

Practical check

Questions for your next design review

  • Does each view answer an identified concern?
  • Are arrows, ownership and boundaries unambiguous?
  • Do interfaces and entities agree across views?
  • Are architectural assumptions connected to evidence and change triggers?
Key takeaway

An architecture description is useful when a reviewer can follow a concern through views, decisions and supporting evidence.

References and further reading

Educational guidance only. Apply the authorised standards editions, regulations and approved procedures relevant to your product and market. Linked publications support further study; the fictional exercises do not demonstrate compliance.